High Court
High Court Clarifies 'Determinable Contract' for Infrastructure Projects, Denies Interim Stay
The High Court recently held that an EPC contract with a 'for cause' termination clause is not inherently determinable under the Specific Relief Act, 1963. However, it declined to grant interim relief against termination, prioritising public interest in infrastructure projects.
By LuricIO Intelligence
In a significant ruling concerning infrastructure contracts, the High Court recently clarified the interpretation of a "determinable contract" under the Specific Relief Act, 1963, while simultaneously denying interim relief sought by a contractor against the termination of an EPC (Engineering, Procurement, and Construction) agreement. The Court underscored that a contract terminable only upon specified defaults, following notice and an opportunity to cure, is not rendered inherently determinable merely by the presence of a termination clause.
The Dispute and the Interim Relief Application
The matter arose from an EPC contract dated October 17, 2022, between Roadway Solutions India Infra (petitioner) and NHAI (respondent) for a highway project, with an original completion date of January 12, 2025. Disputes emerged regarding project delays, with the petitioner citing NHAI's failure to provide right of way and obtain approvals, and the respondent alleging the petitioner's inadequate resource deployment and non-compliance. Despite a settlement agreement on April 25, 2025, revising the completion date to April 30, 2026, disputes persisted. NHAI subsequently issued a cure period notice on January 2, 2026, followed by a notice of intention to terminate on July 16, 2026, under Clause 23.1(ii) of the contract. The petitioner then approached the High Court under Section 9 of the Arbitration and Conciliation Act, 1996, seeking an injunction to restrain NHAI from acting on the termination notice, pending arbitration.
Interpreting 'Determinable Contract' under Specific Relief Act
The High Court, in its analysis, focused on whether the EPC contract was a "determinable contract," which would preclude the grant of specific performance or an injunction under Section 14(d) and Section 41(e) of the Specific Relief Act, 1963, respectively. The Court distinguished between contracts terminable "at will" or "without cause" and those terminable only upon specified defaults after due notice and an opportunity to cure. Relying on the Supreme Court's pronouncement in K.S. Manjunath v. Moorasavirappa, the High Court held that the presence of a termination clause (like Clause 23 in this case) that requires specific contractor defaults, notice, and a cure period, does not automatically make the contract inherently determinable. Therefore, the EPC contract was found not to be determinable in nature under Section 14(d), thus removing a statutory bar to interim relief.
The Triad Test and Public Interest Considerations
Despite finding the contract not determinable, the Court proceeded to evaluate the petitioner's request for interim relief based on the established triad of a prima facie case, balance of convenience, and irreparable injury. Citing Arcelor Mittal Nippon Steel (India) Ltd. v. Essar Bulk Terminal Ltd., the Court found that the petitioner failed to establish a prima facie case against the termination. The Court noted that the validity of the cure period notice had to be assessed against the alleged defaults, and since the notice of intention to terminate was issued after the cure period expired, the petitioner could not prima facie demonstrate a curtailment of the contractual cure period. The merits of the alleged defaults were deemed matters for the Arbitral Tribunal.
Crucially, the Court also considered the public infrastructure aspect, referencing Sections 20A and 41(ha) of the Specific Relief Act, 1963, which restrict injunctions that impede or delay infrastructure projects. Drawing upon precedents such as NHAI v. Roadway Solutions India Infra Limited and NG Projects Ltd. v. Vinod Kumar Jain, the High Court reiterated that courts should generally exercise restraint in interfering with public infrastructure projects. It emphasized that while a wrongful termination could be compensated monetarily through arbitration, delays in highway construction cause significant public loss. Consequently, the balance of convenience was found to favour NHAI and the public at large, and the petitioner's potential injury was deemed primarily commercial and compensable in monetary terms. The interim relief was thus declined, and the petition dismissed, with all observations strictly confined to the Section 9 proceedings, leaving the parties' rights before the Arbitral Tribunal open.
Implications for Infrastructure Contracts
This judgment reinforces the principle that while contracts with 'for cause' termination clauses are not automatically deemed determinable, courts will meticulously apply the interim relief triad, especially when public infrastructure projects are involved. It highlights the judiciary's inclination to protect public interest and prevent delays in critical projects, even where a statutory hurdle for specific performance has been overcome. Contractors in such projects must be prepared to demonstrate a strong prima facie case and significant irreparable injury, beyond mere commercial loss, to secure interim injunctions against termination.
The Specific Relief Act, 1963, governs the remedies available for the enforcement of civil rights, including specific performance of contracts and injunctions. Section 14(d) of the Act prevents the specific enforcement of contracts that are "in their nature determinable," meaning those that can be terminated by either party. Section 41(e) further states that an injunction cannot be granted to prevent the breach of a contract that cannot be specifically enforced. The interpretation of "determinable contract" has evolved, with courts distinguishing between contracts terminable at will and those terminable only for cause. The Arbitration and Conciliation Act, 1996, provides for interim measures by courts under Section 9 to protect the subject matter of arbitration, ensuring that arbitral proceedings remain effective.
This ruling means that even if a contract for public infrastructure (like a highway) is not easily terminable, courts will be hesitant to stop its termination if it risks delaying the project. For citizens, this generally supports the timely completion of essential public services, as the courts prioritize the broader public good over individual contractual disputes that can be settled later with monetary compensation. It implies that disruptions to public works due to legal challenges will be minimised.
Have a question on this?
Ask LuricIO AI about this judgement, the provisions involved, or your own matter, and get a court-ready answer.
This is LuricIO's independent analysis. For the original report, quotes, and full coverage, read the source.
LuricIO Intelligence's AI-generated analysis of this development and the law behind it. It may contain errors and is not legal advice, independently verify the facts and the primary source against the official record before relying on it.
Related analyses
See all in High CourtsDelhi High Court
Delhi High Court Directs SAP to Restore Services to Nayara Energy Despite EU Sanctions
4 min read
Supreme Court of India
Former SC Judge Advocates for Robust Domestic Arbitration Before Global Ambitions
3 min read

Gujarat High Court Arbitration Centre
GHAC Arbitration Week 2026 to Bolster India's Arbitration Landscape
3 min read

Supreme Court of India
Re-evaluating Arbitration's Efficacy: Beyond Systemic Failure to Strategic Reform
4 min read